Grid Connection

Owner

Sharm EL-Shekh City Council
  

Execution year

1999
 

Description

ASET is the first to install a grid connection system in Egypt. The system was constructed to feed electricity generated by the solar modules to the public grid in Sharm EL-Shekh City and South Sinai. The system generates approximately 5 KWH/Day.
 

Main Feature

Solar Modules: (12) SP75 Siemens Solar Modules with a total Capacity of 900 Wp

Grid Inverter : 1.1 KVA Siemens Grid Inverter.